First National Bank "B" Lease

Site 5B

Click on pictures to expand

April 26, 2008

Pump back running, pressure still between 600 and 800 lbs.  Have not received any copy of any notice stating the lease severance has ended.

April 12, 2008

Lease severance issued on B lease April 1, 2008

 due to failure to provide proof of injection well mechanical integrity test.  Pump was

not observed running on this date.

March 29, 2008

Pump  leaking at top and on bottom, saltwater containment device at bottom is not catching all the drips,

pressure close to 800 lbs??

March 8, 2008

February 9, 2008

Salt water containment device

January 6, 2008

  Water pump below leaking, pressure over 400 lbs??

December 30, 2007

 

October 13, 2007

April 20, 2007

 

 

October 28, 2006